Strength and Conditioning Center
Click on the images to enlarge.
Ceiling being removed. Raquetball court walls being removed.
View from the former cardio equipment space. Lower level demolition.
Future weight room when deck is installed. Space will become new dance studio.
Windows cut into exterior walls. The weight room floor has been laid (9/4/09)
Decking
installed over old squash
court
Welding of beams over new dance
studio
(9/17)
(9/17)
View from southwest corner of future Concrete for floor poured (9/21) strength and conditioning center (9/17)
East End of S & C Center Window Opening facing women's locker room
Powerlifting section over old squash court Stairwell leading to courts and dance studio
Dance studio from downstairs hallway Dance studio windows, drywall installation
View from east end of SRC (11/24/09) Power lifting corner (11/24/09)
Outside Entrande to dance studio (11/24/09) Dance Studio with windows and drywall (11/24/09)
Mirrors (left) & glass (top right) installed (12/3) Mirrors installed in powerlifting corner (12/3)
Wood Paneling begins on stairwell (12/3) Floor ready to be installed in Dance Studio (12/3)
Equipment has arrived! View from entrance
Powerlifting corner Putting the finishing touches on the dance studio